Delays and Exctuses: Aren't public getting fed up?
March 10, 2009
Bhargav Sura
The much awaited sea link's opening has yet been delayed from May 1 2009 to June 2.
While they say it is due to the upcoming elections and their code of conducts, there might be a slight hint of the sea link not being completed on time. This is just going to be another excuse for them to delay the sea link's opening.

Source: NatureKnights on PicasaWeb.com (Click Here for a Full Size Image)
Reliance-Hyundai likely to bag Worli-Haji Ali project
The announcement of Worli-Haji Ali stretch of the sealink going to the Reliance-Hyundai consortium seems to be a mere formality now. The MSRDC has recommended to the state that the consortium—which has quoted the lowest government share in the project expenses—should be considered for the contract. “However, the state will announce its final decision only after the elections because the code of conduct is now in place,’’ said MSRDC chairman Vimal Mundada. (Source: TNN)
Click here for previous articles.
Description | Unit | Total Scope | Progress in February 2009 | Total Progess Including Februaary 2009 |
Pile | Nos | 618 | 16 | 618 |
Pile Cap Including Open Foundation | Nos | 139 | 5 | 132 |
Pier Abutment | Nos | 147 | 4 | 133 |
Segment Casting | Nos | 2310 | 68 | 2127 |
Segment Erection | Span | 125 | 9 | 89 |
Bandra Cable Stay P19 | Lifts | 84 | 0 | 84 |
Worli Cable Stay P27 | Lifts | 36 | 0 | 36 |
Worli Cable Stay P30 | Lifts | 34 | 0.5 | 34 |
Progress Table, Courtesy of BandraWorliSealink.com