Delays and Exctuses: Aren't public getting fed up?
March 10, 2009
Bhargav Sura
 
The much awaited sea link's opening has yet been delayed from May 1 2009 to June 2.
 
While they say it is due to the upcoming elections and their code of conducts, there might be a slight hint of the sea link not being completed on time. This is just going to be another excuse for them to delay the sea link's opening.
 

 

Source: NatureKnights on PicasaWeb.com (Click Here for a Full Size Image)



Reliance-Hyundai likely to bag Worli-Haji Ali project

The announcement of Worli-Haji Ali stretch of the sealink going to the Reliance-Hyundai consortium seems to be a mere formality now. The MSRDC has recommended to the state that the consortium—which has quoted the lowest government share in the project expenses—should be considered for the contract. “However, the state will announce its final decision only after the elections because the code of conduct is now in place,’’ said MSRDC chairman Vimal Mundada. (Source: TNN)
 
Click here for previous articles.

 Description

Unit

Total Scope

Progress in February 2009

Total Progess Including Februaary 2009

Pile

Nos

 618

16

618

 Pile Cap Including

Open Foundation

 Nos

 139

5

132

Pier Abutment

 Nos

 147

4

133

Segment Casting

 Nos

 2310

68

 2127

Segment Erection

 Span

 125

9

89

Bandra Cable

Stay P19

Lifts

 84

0

84

Worli Cable

Stay P27

 Lifts

 36

0

36

Worli Cable

Stay P30

 Lifts

 34

0.5

34

Progress Table, Courtesy of BandraWorliSealink.com